Comparison between PROJECT COMMANDER and MICROSOFT PROJECT


Contents
General
Facility summary
Task bars
Layout
Non-working time
Progress reporting
Resource reporting
Cost reporting
Export to Excel
.. Word/Powerpoint
Plan distribution


Major differences between Project Commander and Microsoft Project
Illustrated examples follow on later pages.


General

Project Commander Microsoft Project 2003/7

Multiple levels of UNDO Only one (and on a limited set of functions). 2007 multi undo.

WYSIWYG - what you see on screen is printed exactly You have to go to Print Preview to display output

Shift project facility - one click to move all or part of the project forward or backwards in time Not possible

Consolidation of individually resourced projects Resource information can only be consolidated using a resource pool

Reports combining chart and cost/resource graph Not possible

Over 50 views No

Each view defaults to an appropriate table No

A large selection of watermarks on printouts No watermarks

Facility to insert graphics file/clipart anywhere on page Not possible

Presentation - Bars

Project Commander Microsoft Project

Multiple bars/symbols per line Nothing more than split bars

Colour multiple bars/lines separately Not possible

Automatical colouring by resource All bars would need to be coloured manually

Critical path calculation Not possible

Risk durations Not possible

Sub task colours/text rollup to summary level Not possible

Presentation - Layout

Project Commander Microsoft Project

Border facility Only the basic header/footer

Task headings Only summary bar headings

Cell colouring No facility

Numbering of tasks only No facility

User-defined legends No facility

User text at 90° angle No facility

Presentation - Non-working time

Project Commander Microsoft Project

Show weekends and holidays on weekly charts Not possible

Show weekend and weekday working on weekly charts Not possible

On daily charts exclude non-working days Not possible

On hourly charts exclude non-working days Not possible

Progress task reporting

Project Commander Microsoft Project

Comparison of actual % to scheduled % progress No facility

Comparison of actual % to baseline % progress No facility

Progress line Not a clear jagged progress line

Task days ahead/behind No facility

Resource reporting

Project Commander Microsoft Project

Stacked histograms No facility

Multiple histograms No facility

Combination of chart and resource data No facility

Viewing of tasks by resource No facility

Cost reporting

Project Commander Microsoft Project

Combined chart and cost data Not possible

Cost totals st bottom of chart Not possible

Actual cost vs baseline graph Not possible

Resource costs on graph Not possible

Progress reporting Not possible

Cost per day Not possible

Cost analysis Microsoft Project has User Cost fields – but these do not add up into Total Cost

Actual cost Microsoft Project calculates Actual Cost as the % Complete of the Total Cost and has no Forecast Cost option

Export

Project Commander Microsoft Project

All task data to Excel in a click Not possible

All resource assignment data at a click Not possible

All periodic cost data at a click Not possible

Paste report to Word or Powerpoint Not possible

Distribution

Project Commander Microsoft Project

Free viewer Not available  


Note: This list is not comprehensive and was compiled by PMSC to show clearly areas of superiority. We do not accept any responsibility for any inaccuracies or deficiencies. The comparison is with Microsoft Project standard version.